Time and Work aptitude questions | SBI PO MAIN Exam-2017 | Shortcut Technique | By Amar Sir - Videos

24
228

Please watch: “Data Inequality Questions: 13: Quadratic Equations and Others: SBI PO PRE 29-04-2017: By Amar Sir”


-~-~~-~~~-~~-~-

Amar Sir’s Math Tricks: Quicker Method: Just in few seconds: Without using pen and paper: SBI PO/ Clerk/ IBPS PO/ Clerk/ SSC CGL/ Railway/ RRB/ LIC/ NDA/ CDS/ IAS/ JPSC/ BPSC: By Amar Sir having an experience of 23 years of teaching: Director of Chanakya Career Academy, Jamshedpur: 099311344759334476175

source

24 COMMENTS

  1. sir question me aisa diya h na A is able to finish a job in 60days..mene aise solve kiya toh answer to sahi aa rhe h lkn individual days required galat ayega…please clear my doubt

  2. Q1>>>>>>
    A:B>EF(3:1)>TIME(1:3) MEANING IF A DOES IT IN 60,B WILL TAKE 180 DAYS,LCM(A&B )-180 UNITS
    REMANING WORK BY (B+C) TO DO 180×1/3=60 UNITS,GIVEN THEIR TIME =10 DAYS,MEANING THEIR ''EF(B+C)=60/10=6''
    SIMILARLY FOR A&D ,EF(A+D)=45/5=9

    NOW,ADD BOTH EQU,EF(A+B+C+D)=6+9=15
    SO,THEY DO THE COMPLETE WORK IN 180/15=12 DAYS

    Q2>>>>

    (A+B)1ST DAY +(B+C)2ND DAY +(C+D)3RD DAY +(D+A)4TH DAY =2(A+B+C+D) IN 4 DAYS =2×15=30(EF)

    SO, THEY WILL COMPLETE THE WORK IN 180/30 X4 =24 DAYS

    SIR,
    PLS TELL ME >>>>>>THIS WAY IS CORRECT OR NOT????????????????????